TM 11-6625-3081-23
2-66. TEST FIXTURE REPLACEMENT
2-66
Test fixtures are removed and installed as required by data displayed on video
display terminal for the TPS in use.
2-67. TPS CABLE ASSEMBLY REPLACEMENT
2-67
CAUTION
When connecting zero-force connectors to equipment,
ensure that male connector is seated squarely onto
female connector.
Do not apply uneven pressure. When
turning locking lever, discontinue if resistance is
felt, and inspect connectors for bent pins.
Cables are removed and installed as required by data displayed on video display
terminal for the TPS in use.
2-68. SELF-TEST CONNECTOR REPLACEMENT
2-68
Self-test connectors are removed and installed as required by data displayed on
video display terminal for the TPS in use.
2-320
Change 9