TM 11-6625-3081-23
2-16. SELF-TEST INSTRUCTIONS
2-16
a.
SCOPE
This section provides setup and initialization requirements, instructions on how
to exercise the self-test modules, and external cables and equipment requirements.
b. SETUP AND INITIALIZATION REQUIREMENTS
The following actions must be performed before exercising self-test modules:
(1) Save the calibrate file.
Refer to TM 11-6625-2773-12 for procedure.
(2) Boot up the system.
Refer to TM 11-6625-2773-12 for procedure.
(3) Perform system power up (TM 11-6625-3085-12). If entering self-test from
an operating system, proceed to step 4.
(4) Restore the calibration file.
Refer to TM 11-6625-2773-12 for procedure.
(5) If EETF uses DG S130 computer, load MTØ:Ø of self-test tape 13083904-17.
If EETF uses DG MV7800 computer, load @MTBØ:Ø of self-test tape 13083904-620. Refer
to TM 11-6625-2773-12 for procedure.
(6) Set video display and printer interface select switches to on. Refer to
TM 11-6625-3085-12 for procedure.
(7) Connect extender assembly 37203A power cord to 115v 60 Hz. Set MASTER/
SLAVE switch on rear of extender assembly to MASTER and SERIAL DATA RATE switch on
rear of extender assembly to NORMAL.
(8) Connect cable assembly 13081454-29 from rear of extender assembly COAXIAL
to electronic station cable entry panel 1A13J4.
(9) Connect cable HPIB10833C or HPIB10631C from rear of extender assembly HPIB
to A21J6 of the AN/USM-410 VDT.
(10) Allow a minimum of 2 hours warmup of PMT controller 1A7, if PMT/LED module
is to be exercised.
c.
EXERCISING SELF-TEST MODULE
The operator performs setup and initialization actions then enters TEST followed
by EOBST to start the menu driven self-test program. The following screen display
will appear on the AN/USM-410 VDT.
Change 20
2-95