Section III.
PREVENTIVE MAINTENANCE CHECKS AND SERVICES (PMCS)
TM 11-6625-3081-23
Subject
Para
Page
General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2-10
2-39
PMCS Procedures. . . . . . . . . . . . . . . . . . . . . . . . . .
2-11
2-39
2-10. GENERAL
2-10
To ensure that the EETF TADS/PNVS Augmentation Equipment is ready for operation
at all times, it must be checked at regular intervals. These checks may uncover
defects that must be corrected before they cause serious damage or failure.
2-11. PMCS PROCEDURES
2-11
PMCS information is contained in the following table. The following is an
explanation of the column headings in the table.
a. The Item No. column contains the item number in logical order of perform-
ance regardless of interval.
This column shall be used as a source of item
numbers for the TM Number Column on DA Form 2404, Equipment Inspection and
Maintenance Worksheet, in recording results of PMCS.
b.
The Interval column tells you when to perform the PMCS; D (daily), M
(monthly), Q (quarterly), S (semiannually), 8 (every 8 months), and
A (annually).
c.
The Item to be Inspected/Procedure column identifies the equipment area,
the exact item of equipment, and procedures. Procedures that are too
lengthy to be included in the table are referenced elsewhere in this
manual .
d.
The Reference/Remarks column references the procedure to be used to
perform repairs/replacements (maintenance) should a defect be found while
performing the PMCS.
Where an operational check is to be performed, it is
referenced as operation.
Change 9
2-39